Friday, April 29, 2011

Here We Go


Building permit displayed per county code


Skid loader cuts in culvert along front of lot.


Culvert will be covered then rock on top to form base of driveway.


Silt fence prevents dirt run off when it rains.


Dozer scrapes off rich top soil to be piled up and used upon completion.


Moving top soil.


Teamwork!


Pile #1.

Next Steps?

Haul in rock for drive.
Stake out the location of the foundation.
Bring in excavator to dig basement.
Excess dirt will be used by the maintenance department as repair fill for trails.
Once the basement digging is complete then the concrete contractor will take over.